January 28, 2016

Smith Construction Update

Img_4223

2016 is already off to a successful start, the energy is high on the Smith site as construction continues to progress daily. The CANA construction team has successfully completed the 11th level with just seven more levels to go!

As Smith continues to grow upwards the crane has also been extended to its full height of 189.45 feet tall! Early in January the window installation commenced allowing steel stud framing to begin on levels three and four. As the exterior continues to transform, next will be the interior. The interior finishes and appliances are scheduled to arrive in the later part of February.

Don’t forget to view our facebook construction page to keep up to date with Smith’s progress.